DPWH looks to finish Estrella-Pantaleon Bridge by mid-2021 amid restrictions

Estrella-Pantaleon bridge

As the Department of Public Works and Highways (DPWH) announced the latest guidelines for the implementation of infrastructure allowed projects, the agency said it is keen on completing the Estrella-Pantaleon Bridge by midyear.

According to DPWH Secretary Mark Villar, the project is now at 86 percent completion, and the agency taking the progress in two folds: the civil works for the targeted completion and maintaining the healthy and safe workplace amid the threat of the COVID-19.

Villar, who earlier tested positive for the dreaded virus, said that they are still mindful that a single case could hamper the project, saying that it could lead to interruption or worse, total work stoppage. 

Estrella-Pantaleon Bridge

Recently, the public works secretary issued revised guidelines contained in Department Order 30 for the implementation of allowed infrastructure projects, both public and private, during the public health crisis under enhanced community quarantine (ECQ), modified ECQ, general community quarantine (GCQ) and modified GCQ.  

“Although the bridge project is being rushed for completion in June 2021, it is critical that construction firms be proactive rather than reactive in dealing with the increased risk of illness from COVID-19,” Villar noted.  

Last April 5, Undersecretary for Unified Project Management Office (UPMO) Operations Emil Sadain and UPMO Roads Management Cluster 1 Project Manager Benjamin Bautista checked the physical progress of the project and the compliance to protocols that Villar has set.

Estrella-Pantaleon Bridge

“Let’s get to work healthy to get the job done”, Sadain reminded the contractor, China Road and Bridge Corporation, highlighting the situation within the Greater Manila Area (now being identified by the government as National Capital Region Plus bubble).   

Sadain stated in his report that the project progress of 86 percent is more than 12 percent ahead of schedule, having completed all bridge substructure works for abutments A and B at both sides and piers of Makati approach bridge; the V-shaped piers for the Main Bridge; concrete box girder for the approach bridge; 20 segments of prestressed concrete box girder for the main bridge using form traveler system; and two segments of prestressed concrete box girder using conventional method.  

The agency also noted that bridge construction activities are undergoing post-tensioning and grouting works; formworks and rebar installation for the closure section in the side spans; formworks installation for the two-meter closure section in the main bridge span; and preparatory works for approach road construction in both sides.  

Estrella-Pantaleon Bridge

The new 506-linear meter bridge—which was a China-grant project implemented by the DPWH UPMO-Roads Management Cluster 1 (Bilateral)—is 21.65 meters wide, and has grown into four lanes unlike the previous two, with three-meter sidewalks on both sides. 

When completed, the ₱1.46 Billion bridge project can accommodate around 50,000 vehicles daily and is eyed to reduced travel time between cities of Mandaluyong and Makati as well as help decongest EDSA of traffic as it can serve as an alternate route for motorists. 

Prior to this, the closure for the bridgework was deferred many times since 2018, and was finally closed January 2019.

Photos from Department of Public Works and Highways

Also read:

Completion of Estrella-Pantaleon, Binondo-Intramuros Bridges still on schedule

Expect Longer Commute Time Once the Estrella-Pantaleon Rehabilitation Starts This Week

Closure of Estrella-Pantaleon Bridge to Finally Push Through on January 12

Read All

Featured Articles

Recommended Articles For You

Read All

Featured Cars

  • Upcoming

Car Articles From Zigwheels

  • News
  • Article Feature
  • Advisory Stories
  • Road Test
  • BYD to establish presence in 77 locations nationwide this 2025
    BYD to establish presence in 77 locations nationwide this 2025
    Ruben Manahan IV . Apr 17, 2025
  • Honda Cars PH revives HEAT program for Holy Week 2025
    Honda Cars PH revives HEAT program for Holy Week 2025
    Ruben Manahan IV . Apr 17, 2025
  • SMC toll roads ready for Holy Week rush
    SMC toll roads ready for Holy Week rush
    Ruben Manahan IV . Apr 17, 2025
  • Kaiyi Auto enters PH market
    Kaiyi Auto enters PH market
    Ruben Manahan IV . Apr 16, 2025
  • Ford PH’s April promo allows car buyers to get free 3-year scheduled service package
    Ford PH’s April promo allows car buyers to get free 3-year scheduled service package
    Paulo Papa . Apr 16, 2025
  • Here’s what to expect on the road this Holy Week
    Here’s what to expect on the road this Holy Week
    Paulo Papa . Apr 16, 2025
  • Here are some iconic Manila churches you can check out for Visita Iglesia via the NLEX Connector
    Here are some iconic Manila churches you can check out for Visita Iglesia via the NLEX Connector
    Paulo Papa . Apr 16, 2025
  • Suzuki Dzire Hybrid: strengths and weaknesses
    Suzuki Dzire Hybrid: strengths and weaknesses
    Cesar Miguel . Apr 16, 2025
  • Here are some spiritual sanctuaries you can visit this Holy Week via SCTEX
    Here are some spiritual sanctuaries you can visit this Holy Week via SCTEX
    Paulo Papa . Apr 16, 2025
  • Here’s how Prestone can help make your Holy Week getaways safe, hassle-free
    Here’s how Prestone can help make your Holy Week getaways safe, hassle-free
    Paulo Papa . Apr 16, 2025
  • What should you visit first at MIAS 2025?
    What should you visit first at MIAS 2025?
    Cesar Miguel . Apr 11, 2025
  • Do you really need 4x4 for overlanding?
    Do you really need 4x4 for overlanding?
    Cesar Miguel . Mar 26, 2025
  • Number coding 2025: what you need to know
    Number coding 2025: what you need to know
    Paulo Papa . Mar 09, 2025
  • EVs still require lubrication, JAMA execs say
    EVs still require lubrication, JAMA execs say
    Paulo Papa . Mar 09, 2025
  • Ensure your vehicle is Summer road trip-ready by following these tips
    Ensure your vehicle is Summer road trip-ready by following these tips
    Paulo Papa . Mar 06, 2025
  • First drive: Jetour X70 Lightning i-DM
    First drive: Jetour X70 Lightning i-DM
    Paulo Papa . Apr 03, 2025
  • Changan CS15: no-fuss daily driver
    Changan CS15: no-fuss daily driver
    Cesar Miguel . Mar 27, 2025
  • First drive: Mercedes-Benz EQE 350+ AMG Line
    First drive: Mercedes-Benz EQE 350+ AMG Line
    Paulo Papa . Mar 21, 2025
  • BYD Shark 6 DMO: first impressions
    BYD Shark 6 DMO: first impressions
    Cesar Miguel . Mar 19, 2025
  • Changan Uni-T: bold and classy
    Changan Uni-T: bold and classy
    Ruben Manahan IV . Mar 14, 2025